Progress claim template for trades

Reconcile completed work, variations, retention and earlier claims, then keep dates and evidence with the claim.

Progress claims need a clear trail from completed work to the amount requested. This progress claim template keeps the contract, variations, retention, earlier claims and payment records together.

The short answer: download the blank and SAMPLE files, then replace the assumptions with your own records. Check your state’s Act and your contract before using the document. Get construction-law advice for a dispute.

CLAIMSTAGESCLAIMED: 2 OF 4claimed so far,and what is left
What has been claimed, and what is left.

Download the claim record

SAMPLE, NOT FOR ISSUE: A$23,750.00 before GST + A$2,375.00 GST = A$26,125.00 this claim.

Six files, three formats.

What each format gives you, blank and SAMPLE
FormatBlank and SAMPLE
WordEditable fields, manual totals
ExcelVisible formulas and input checks
PDFPrintable record, manual totals

The files contain the same business fields. They include a claim summary, twenty work lines, a dates diary and an evidence index. Nothing in a file serves a claim, confirms an entitlement or chooses a deadline.

Keep one claim reference and revision across the files. Use the quote template for the earlier offer. Use the work order for the crew’s instruction and visit record. This download follows the completed work into the claim record.

The complete blank and SAMPLE records appear here, with matching fields.

Blank record, every field

BLANK TEMPLATE: complete and review before use. Progress claim WB-PC-2026-11-06-v1.

A claim document you adapt. It does not decide whether it meets your Act or contract: check both, and get advice for a dispute. Not a tax invoice.

Claim

Row 6: Project reference
Empty
Row 7: Claim reference
Empty
Row 8: Claimant record
Empty
Row 9: Respondent record
Empty
Row 10: Contract reference and date
Empty
Row 11: Job and scope description
Empty
Row 12: State or territory
Empty
Row 13: Work period starts
Empty
Row 14: Work period ends
Empty
Row 15: Prepared date
Empty
Row 16: Claim document date
Empty
Row 17: Actual service record
Empty
Row 18: Contract stage/payment schedule reference
Empty
Row 19: Payment schedule response date, entered
Empty
Row 20: Payment due date, entered
Empty
Row 21: Date basis, source and responsible role
Empty
Row 22: Original contract sum, A$ excluding GST
Empty
Row 23: Retention held to date, A$ excluding GST
Empty
Row 24: Retention held before this claim, A$ excluding GST
Empty
Row 25: GST on this claim, entered A$
Empty
Row 26: Confirmed tax basis/reference
Empty
Row 27: GST on previous claims, entered A$
Empty
Row 28: Payments against previous claims, A$ including GST
Empty
Row 29: Current assessed/certified amount, A$ including GST
Empty
Row 30: Reviewer role
Empty
Row 31: Release decision
Hold
Row 32: Next action
Empty
Row 33: Previous claim reference(s)
Empty
Row 34: Arithmetic state
Formula in Excel; manual check in Word and PDF

Results (Excel calculates; Word and PDF are worked by hand)

Row 36: Revised contract, A$ excluding GST
Empty
Row 37: Base work completed to date, A$ excluding GST
Empty
Row 38: Variations completed to date, A$ excluding GST
Empty
Row 39: Completed value to date, A$ excluding GST
Empty
Row 40: Previous gross work claimed, A$ excluding GST, before retention
Empty
Row 41: Current gross work movement, A$ excluding GST, before retention
Empty
Row 42: Retention movement on this claim, A$ excluding GST
Empty
Row 43: This claim, A$ excluding GST, after retention
Empty
Row 44: Entered GST on this claim, A$
Empty
Row 45: This claim, A$ including GST
Empty
Row 46: Cumulative claim, A$ excluding GST, after retention
Empty
Row 47: Previous claim, A$ excluding GST, after prior retention
Empty
Row 48: Previous GST, entered A$
Empty
Row 49: Previous claims, A$ including GST
Empty
Row 50: Previous unpaid balance, A$ including GST
Empty
Row 51: All claims including this one, A$ including GST
Empty
Row 52: Retention held to date, A$ excluding GST
Empty
Row 53: Unclaimed contract value, A$ excluding GST, before retention
Empty
Row 54: Previous receipts, A$ including GST
Empty
Row 55: Current assessment, A$ including GST
Empty
Row 56: Current assessment less current claim, A$ including GST
Empty

Document fields

Row 58: Applicable wording/forms to obtain
Empty
Row 59: Document boundary
A claim document you adapt. It does not decide whether it meets your Act or contract: check both, and get advice for a dispute. Not a tax invoice.
Row 60: Saved record location
Empty
Row 61: Revision
Empty
Row 62: Notes
Empty
Row 63: Actual claimant identity, ABN and applicable licence details
[claimant identity, ABN and licence details where applicable]
Row 64: Actual respondent identity and applicable ABN
[respondent identity and ABN where applicable]
Row 65: Verified payment instructions
[verified payment instructions]
Row 66: Additional required wording/forms and attachments
[additional wording, forms and attachments required for your job]

Work lines

Work lines W01 to W20 for the blank progress claim, in Australian dollars
Line IDTypeContract item or variation descriptionAllocated contract value, A$ excl. GSTCompleted value to date, A$ excl. GSTPreviously claimed gross work value, A$ excl. GST, before retentionContract or variation authority referenceWork evidence referenceThis claim, gross, A$ excl. GST
W01
W02
W03
W04
W05
W06
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
Work totals for the blank progress claim, in Australian dollars
TotalsAllocated contract value, A$ excl. GSTCompleted value to date, A$ excl. GSTPreviously claimed gross work value, A$ excl. GSTThis claim, gross, A$ excl. GST
All active work
Base totals
Variation totals

Dates diary

Dates D01 to D07 for the blank progress claim
Event IDEventDate enteredActual record/statusSource or basisResponsible roleNext action
D01Work period ends
D02Prepared
D03Planned service
D04Payment schedule response date
D05Payment due date
D06Internal follow-up
D07Retention review

Evidence index

Evidence EV-PC-01 to EV-PC-05 for the blank progress claim
Evidence IDRelated claim/lineRecord or file referencePurposeOpened by role/dateResultAction
EV-PC-01
EV-PC-02
EV-PC-03
EV-PC-04
EV-PC-05
SAMPLE record, not for issue

SAMPLE, NOT FOR ISSUE: illustrative records, not client data. Progress claim WB-PC-2026-11-06-v1.

A claim document you adapt. It does not decide whether it meets your Act or contract: check both, and get advice for a dispute. Not a tax invoice.

Claim

Row 6: Project reference
JOB-SAMPLE-7201
Row 7: Claim reference
PC-SAMPLE-7203
Row 8: Claimant record
Contractor A, sample
Row 9: Respondent record
Customer A, sample
Row 10: Contract reference and date
CONTRACT-SAMPLE-7201, 1 September 2026
Row 11: Job and scope description
Sample commercial maintenance fit-out, packages W01 to W03
Row 12: State or territory
Not set: select your state or territory
Row 13: Work period starts
1 October 2026
Row 14: Work period ends
31 October 2026
Row 15: Prepared date
6 November 2026
Row 16: Claim document date
6 November 2026
Row 17: Actual service record
Not served: SAMPLE specimen
Row 18: Contract stage/payment schedule reference
SCHEDULE-SAMPLE-01; reference only, no legal form supplied
Row 19: Payment schedule response date, entered
DATE NOT SET: obtain and enter the confirmed dates
Row 20: Payment due date, entered
DATE NOT SET: obtain and enter the confirmed dates
Row 21: Date basis, source and responsible role
Not set: the response and payment dates depend on your Act and contract. Enter the confirmed dates, their source and the responsible role, and get advice.
Row 22: Original contract sum, A$ excluding GST
120,000.00
Row 23: Retention held to date, A$ excluding GST
3,250.00
Row 24: Retention held before this claim, A$ excluding GST
2,000.00
Row 25: GST on this claim, entered A$
2,375.00
Row 26: Confirmed tax basis/reference
SAMPLE assumption only: 10% of current net claim after retention. Not tax advice; confirm the actual taxable amount and timing.
Row 27: GST on previous claims, entered A$
3,800.00
Row 28: Payments against previous claims, A$ including GST
33,000.00
Row 29: Current assessed/certified amount, A$ including GST
Empty: assessment not received
Row 30: Reviewer role
Office reviewer role, sample
Row 31: Release decision
Hold
Row 32: Next action
Replace every SAMPLE record, confirm legal and tax position, then review saved document and attachments.
Row 33: Previous claim reference(s)
PC-SAMPLE-7202
Row 34: Arithmetic state
ARITHMETIC VALID

Results (Excel calculates; Word and PDF are worked by hand)

Row 36: Revised contract, A$ excluding GST
A$125,000.00
Row 37: Base work completed to date, A$ excluding GST
A$60,000.00
Row 38: Variations completed to date, A$ excluding GST
A$5,000.00
Row 39: Completed value to date, A$ excluding GST
A$65,000.00
Row 40: Previous gross work claimed, A$ excluding GST, before retention
A$40,000.00
Row 41: Current gross work movement, A$ excluding GST, before retention
A$25,000.00
Row 42: Retention movement on this claim, A$ excluding GST
A$1,250.00
Row 43: This claim, A$ excluding GST, after retention
A$23,750.00
Row 44: Entered GST on this claim, A$
A$2,375.00
Row 45: This claim, A$ including GST
A$26,125.00
Row 46: Cumulative claim, A$ excluding GST, after retention
A$61,750.00
Row 47: Previous claim, A$ excluding GST, after prior retention
A$38,000.00
Row 48: Previous GST, entered A$
A$3,800.00
Row 49: Previous claims, A$ including GST
A$41,800.00
Row 50: Previous unpaid balance, A$ including GST
A$8,800.00
Row 51: All claims including this one, A$ including GST
A$67,925.00
Row 52: Retention held to date, A$ excluding GST
A$3,250.00
Row 53: Unclaimed contract value, A$ excluding GST, before retention
A$60,000.00
Row 54: Previous receipts, A$ including GST
A$33,000.00
Row 55: Current assessment, A$ including GST
Not received
Row 56: Current assessment less current claim, A$ including GST
Not available

Document fields

Row 58: Applicable wording/forms to obtain
Not supplied: confirm for actual jurisdiction, contract and role.
Row 59: Document boundary
A claim document you adapt. It does not decide whether it meets your Act or contract: check both, and get advice for a dispute. Not a tax invoice.
Row 60: Saved record location
SAMPLE folder / JOB-SAMPLE-7201 / PC-SAMPLE-7203
Row 61: Revision
1, SAMPLE
Row 62: Notes
No actual work, approval, service, payment or legal review is asserted by this specimen.
Row 63: Actual claimant identity, ABN and applicable licence details
[insert verified actual details]
Row 64: Actual respondent identity and applicable ABN
[insert verified actual details]
Row 65: Verified payment instructions
[insert independently verified payment instructions]
Row 66: Additional required wording/forms and attachments
Not supplied: obtain for the actual job

Work lines

Work lines W01 to W20 for the sample progress claim, in Australian dollars
Line IDTypeContract item or variation descriptionAllocated contract value, A$ excl. GSTCompleted value to date, A$ excl. GSTPreviously claimed gross work value, A$ excl. GST, before retentionContract or variation authority referenceWork evidence referenceThis claim, gross, A$ excl. GST
W01BaseSample package AA$80,000.00A$48,000.00A$32,000.00CONTRACT-SAMPLE-7201 AEV-PC-02A$16,000.00
W02BaseSample package BA$40,000.00A$12,000.00A$8,000.00CONTRACT-SAMPLE-7201 BEV-PC-02A$4,000.00
W03VariationSample additional scope, no real approval assertedA$5,000.00A$5,000.00A$0.00VAR-SAMPLE-7201EV-PC-03A$5,000.00
W04
W05
W06
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
Work totals for the sample progress claim, in Australian dollars
TotalsAllocated contract value, A$ excl. GSTCompleted value to date, A$ excl. GSTPreviously claimed gross work value, A$ excl. GSTThis claim, gross, A$ excl. GST
All active workA$125,000.00A$65,000.00A$40,000.00A$25,000.00
Base totalsA$120,000.00A$60,000.00A$40,000.00A$20,000.00
Variation totalsA$5,000.00A$5,000.00A$0.00A$5,000.00

Dates diary

Dates D01 to D07 for the sample progress claim
Event IDEventDate enteredActual record/statusSource or basisResponsible roleNext action
D01Work period ends31 October 2026Period recorded, SAMPLEClaim D14Office role, sampleReconcile W01:W03
D02Prepared6 November 2026Prepared specimen, SAMPLEClaim D15Office role, sampleReplace SAMPLE records
D03Planned service6 November 2026Not servedIllustrative planning date, not an entitlement to serveOffice role, sampleConfirm actual permitted date/method and record receipt evidence
D04Payment schedule response dateNOT SETNot set: SAMPLENot set: depends on your Act and contractAdviser/reviewer role, sampleObtain the job’s actual Act/contract basis
D05Payment due dateNOT SETNot set: SAMPLENot set: depends on your Act and contractAdviser/reviewer role, sampleConfirm the actual due date
D06Internal follow-upNot set: SAMPLEInternal example only, no legal extension inferredOffice role, sampleSet after the confirmed due date
D07Retention reviewNOT SETNot setDepends on actual agreement and adviceContract owner role, sampleObtain the actual trigger and date

Evidence index

Evidence EV-PC-01 to EV-PC-05 for the sample progress claim
Evidence IDRelated claim/lineRecord or file referencePurposeOpened by role/dateResultAction
EV-PC-01PC-SAMPLE-7203CONTRACT-SAMPLE-7201 and scheduleContract and original allocationNot opened: specimenNot openedSample only: obtain and read actual contract
EV-PC-02W01, W02SAMPLE folder / work-period / completion-recordCompleted valuesNot opened: specimenNot openedSample only: obtain actual supporting evidence
EV-PC-03W03VAR-SAMPLE-7201Changed scope and authorityNot opened: specimenNot openedSample only: obtain actual decision and evidence
EV-PC-04PC-SAMPLE-7202SAMPLE folder / prior-claim / 6-OctoberEarlier gross work 40000, retention 2000 and GST 3800Not opened: specimenNot openedSample only: reconcile actual prior claim
EV-PC-05Earlier receiptsRECEIPT-SAMPLE-7201, 30 October 2026Prior illustrative receipt 33000 including GSTNot opened: specimenNot openedSample only: match actual bank record

Renzo Demartini, Chartered Accountant (CA ANZ).

Sources read 6 November 2026.

Drafted with AI, reviewed and spot-checked by me.

General information only, not tax agent or legal advice. Confirm your contract and applicable law with a construction lawyer, and GST treatment with your accountant.

One claim, reconciled

CLAIM 4?what was claimed last time?

Today. Each claim starts with working out what was claimed last time.

CLAIMCOMPLETED WORKVARIATIONSRETENTIONEARLIER CLAIMSit allties uplineby line

Reconcile completed work, variations, retention and earlier claims.

THE CLAIMDATESEVIDENCEkept with the claim

Keep the dates and the evidence with the claim.

An example. The details are made up.

The detail, if you want it

Use it in three steps

Use it in three steps

  1. Prepare

    Contract, prior claim and work evidence

  2. Reconcile

    Completed value, retention, prior claims and GST

  3. Review

    Dates, attachments, authority and saved copy

Start from the contract breakdown. Record completed value against each line, with variations on separate rows. Keep the source reference beside every changed amount. The arithmetic uses cumulative completed value less previous claimed value. It does not substitute cash received for an earlier claim.

Carry the earlier retention and GST records forward separately. Enter the current GST amount confirmed for your work.

The SAMPLE requests A$26,125.00

The SAMPLE requests A$26,125.00

SAMPLE bridge, A$ excluding GST unless shown.

The SAMPLE bridge from completed work to the amount this claim requests, in Australian dollars
SAMPLE bridgeA$, excluding GST unless shown
Base work completed60,000.00
Completed variation5,000.00
Retention held to date(3,250.00)
Previously claimed, after earlier retention(38,000.00)
This claim before GST23,750.00
Entered GST, sample 10%2,375.00
This claim including GST26,125.00

Sample data, not a customer’s claim. The original contract is A$120,000. A sample A$5,000 variation takes it to A$125,000. Completed work totals A$65,000, leaving A$60,000 of contract value unclaimed before retention.

The sample GST is 10% of A$23,750. The ATO’s calculation steps say “calculate 10% of this amount”. [1] That arithmetic does not decide the taxable amount, retention treatment or tax timing for your contract. Ask your accountant before entering GST.

Keep claimed, assessed and paid apart
Record dates without guessing

Record dates without guessing

Where each date comes from.

Where the answer for each date belongs
Date fieldWhere the answer belongs
Claim and serviceActual record and supporting evidence
Payment schedule responseYour applicable Act and contract, with advice
Payment dueYour applicable Act and contract, with advice

The dates diary stores dates you enter. It counts no business days and applies no state rule. The SAMPLE leaves the response and payment dates unset: they depend on your Act and contract. Nothing here establishes when a live claim can be served or paid.

Keep the contract’s stage payment schedule distinct from a respondent’s payment schedule. Record the source, responsible role and next action for each date. A missing date stays visibly unset. Refer to the official links in Sources and ask a construction lawyer when the position is unclear.

Check the saved claim

Check the saved claim

Three checks before release.

Three checks before release and the evidence to keep for each
CheckEvidence to keep
Work and changesContract references and supporting records
AmountsPrior claim, retention and confirmed GST basis
ReleaseResponsible reviewer, revision and saved document

Arithmetic cannot establish authority or legal sufficiency. Open the saved PDF and every listed attachment. Keep the claim, response and receipts as separate records. Use the invoice template for a separate invoice when appropriate to your advised process.

The SAMPLE stays on Hold. Its evidence, dates and decisions are illustrative. General information only, not tax agent or legal advice. Start with a free fit check by email at the foot of this page.

Questions

Questions

What is in the progress claim template?

The six files contain a claim summary, work lines, a dates diary and an evidence index, with identical business headings. Word is editable, PDF is printable, and both use manual totals. Excel adds formulas and input checks, while the SAMPLE editions show how one illustrative claim reconciles.

Can the template confirm a valid payment claim?

No, it records your work and amounts, but it does not decide legal sufficiency, entitlement, service or timing. Check the Act applying to your state or territory and your contract before using it. Get construction-law advice for a dispute, a live response deadline or uncertainty about the required document.

Does it calculate the payment schedule deadline?

The dates diary stores the dates you enter and the evidence behind them. It does not count business days or choose a state rule. Keep the contract’s stage payment schedule separate from the respondent’s payment schedule, and ask your adviser to confirm the dates for your job.

How does the SAMPLE handle retention and GST?

The sample deducts A$3,250 retention held to date and A$38,000 previously claimed after earlier retention from A$65,000 completed value. Its current claim is A$23,750 before an entered A$2,375 GST amount. Those are illustrative assumptions, so ask your accountant about your actual taxable amount, retention treatment and timing.

Why are previous claims different from payments?

The earlier claim records what was requested, while a payment records money received. In the SAMPLE, A$41,800 was claimed earlier and A$33,000 was received, leaving A$8,800 separately unpaid. The workbook keeps that balance apart from the current claim, so a receipt cannot silently change the work-to-date calculation.

Should I use Word, Excel or PDF?

Choose Word to adapt the document, Excel for visible arithmetic, or PDF for a printable blank record. Each format has the same business fields and a filled SAMPLE. Read the saved copy, attachments and dates before sharing it, and keep the claim reference and revision together in your approved location.

Sources

Sources

Sources read 6 November 2026.

Check your state or territory’s current Act and your contract. Ask a construction lawyer about eligibility, required wording, service, response dates and payment dates. Get advice for a dispute.

I get the systems you already have talking to each other and working together, so you get your nights and weekends back and are home for dinner.

Renzo

Renzo Demartini, Chartered Accountant

Works with Xero, MYOB, QuickBooks, n8n and Zapier, your job software, and whatever else you run.

Get a free fit check by email

Send the form with the workflow to fix and your email. Your software, team size and timing are optional, but they help. I reply by email, usually with a question or two, and tell you whether it's a fit. No call needed. If it is, the next step is the A$1,500 Workflow Audit.

Tell me what’s stuckStep 1 · Fit check · free, by email

Optional, but it helps me reply

Sending saves your details in HubSpot so I can reply. No mailing list. No payment is taken. How your enquiry is handled.