A job is half done, nothing is billed and the costs keep landing. Your accounts show it only when the invoice goes out. A WIP report shows it now, job by job.
The short answer: a WIP report lists each open job with its cost so far, what you have billed and what is earned but not billed. Simpro and AroFlo have one.23 ServiceM8’s help pages list none.4 Run it weekly and look at two numbers: unbilled work and cost above plan.
- 01 · QuoteThe job is open
Job app Job 3103 Open
- Bathroom (sample)A$15,000.00
- 02 · CostCosts land on the job
- Materials and labour coded
- Cost so far A$9,000
- 03 · BilledInvoices are added up
Accounts Invoices None
- Billed to dateA$0.00
- 04 · CheckYou read the report
Job 3103: A$7,500 unbilledCost is A$3,375 over plan
At the end of the day Steps 1 to 3 are numbers from your software. Step 4 is your decision.
What a WIP report shows
| Column | What it means | A vendor’s description |
|---|---|---|
| Cost so far | What the job has cost to date | AroFlo: costs incurred between two dates |
| Billed so far | What you have invoiced | AroFlo: invoices raised between two dates |
| Left to bill | The job total less what is billed | Simpro: job total less total billed, excluding tax |
| Over or under billed | Billed against the share done | AroFlo’s Project Over/Under Billings report |
MYOB says “Work in progress is work that you have done for your clients but haven’t billed yet”, and that your records show a sale only when you bill.1 Simpro’s figure for what is not yet billed is the whole job total less what is billed, so ask how much of it is earned.2
What Simpro and AroFlo say about their reports
Simpro says its Job WIP report “displays jobs that were not invoiced in full or archived up to and including the specified date”.2 It says “The date that a job is archived determines whether it appears in this report”.2
AroFlo says its Task Work In Progress (WIP) By Date report is “useful to see what costs were incurred and invoices raised between specified dates”.3 Its Project Over/Under Billings report “answers the question “Am I allowed to invoice more money?””.3
What your software gives you
| Software | Report to use | What it shows |
|---|---|---|
| Simpro | Job WIP report | Jobs not invoiced in full, as at a date |
| AroFlo | Task WIP by Date and Project Over/Under Billings | Costs and invoices in a date range, and over or under billing |
| ServiceM8 | Jobs Completed report | Completed jobs with no invoice sent. No WIP report in its help pages |
| MYOB AccountRight | A month-end journal | Plus and Premier only. Unbilled time on activity slips |
| Xero Projects | Project reports | Cost by task, with what is invoiced and what is to bill |
ServiceM8’s Jobs Completed report has a “Not Invoiced” total: “the total value of Completed jobs which have not had an invoice sent to the client”.4 That counts finished jobs, not open ones. Xero’s page promises “a cost breakdown by task – including what’s been invoiced and what still needs to be billed”.6
Read five open jobs
Unbilled work, A$, sample
Earned less billed, job by job. Job 3102 is billed A$2,400 ahead of the work, so it shows none.
Illustrative figures, not client data.
| Job | Earned | Billed | Unbilled | Cost so far | Over plan |
|---|---|---|---|---|---|
| 3101 Switchboard upgrade | A$7,200 | A$6,000 | A$1,200 | A$5,400 | A$0 |
| 3102 Kitchen rewire | A$5,600 | A$8,000 | A$2,400 ahead | A$5,600 | A$1,400 |
| 3103 Bathroom | A$7,500 | A$0 | A$7,500 | A$9,000 | A$3,375 |
| 3104 Hot water | A$2,000 | A$1,000 | A$1,000 | A$1,600 | A$100 |
| 3105 Shed power | A$2,400 | A$1,500 | A$900 | A$2,400 | A$600 |
| Total | A$24,700 | A$16,500 | A$8,200 net | A$24,000 | A$5,475 |
Sample data, not a client’s, in A$ excluding GST. Earned is the quote times the share done, which the site lead estimates. Plan cost is earned less a 25% quote margin. Over plan is cost so far above plan cost. This is my method, not a standard.
Three jobs hold A$5,375 of the A$5,475 over plan. Job 3102 is billed A$2,400 ahead, which helps cash and hides a cost problem.
The weekly check
- Run it as at today. Simpro’s report is a snapshot up to the date you choose.2
- Sort by unbilled. Bill what the work already supports.
- List jobs over plan. Cost so far above the plan cost.
- Ask for the share done. The site lead updates it on those jobs.
- Write the totals down. Next week’s check compares with them.
The unbilled figure rests on the share done, so use it as a prompt to check. Ask your accountant how work in progress is treated in your books.
Where a person stays in charge
The report
It adds up cost, billed and earned for each open job. It decides nothing.
The site lead
Gives the share done on each job. Every unbilled figure rests on this number.
You
You decide what to bill now and which jobs to review.
For one job costed from start to finish, see job costing for trades. For extra work never invoiced, try the free calculators.
The Job Profit Report puts each job’s costs and billed revenue side by side every week, A$5,900, in 3–4 weeks.7
If you are not sure which workflow to fix first, start with a Workflow Audit for A$1,500. It is a short brief by email and a read-only review of one workflow, up to two connected systems and a four-week sample of its records. The written report gives a clear decision (build it, change a setting or not yet) and a fixed quote if a build is worth doing.7 Start with a free fit check by email at the foot of this page.
Questions
What is a WIP report?
A list of open jobs with what each has cost, what has been billed and what is earned but not billed. MYOB defines work in progress as work you have done for clients but not yet billed.1
Does ServiceM8 have a WIP report?
Its help pages list none. The Jobs Completed report shows a Not Invoiced total for completed jobs, and the Advanced Reporting Pack exports a job list.45
What is the difference between unbilled and over billed?
Unbilled is work done and not yet invoiced. Over billed is invoiced ahead of the work done. AroFlo’s Project Over/Under Billings report is designed to show whether a project is over or under billed.3
How often should I run a WIP report?
Weekly is a sensible rhythm for an owner. Simpro’s report is a snapshot, so each run shows the position at the date you choose.2
Sources
- 1. MYOB, “Work in progress”, read 8 November 2026: www.myob.com/au/support/myob-business/projects/billing-for-time/work-in-progress
- 2. Simpro Help Guide, “Job WIP report”, read 8 November 2026: helpguide.simprogroup.com/articles/#!help-guide/job-wip-report
- 3. AroFlo Help, “Office work in progress reporting”, read 8 November 2026: help.aroflo.com/articles/hg/office-work-in-progress-reporting
- 4. ServiceM8 Help Center, “Jobs Completed Report”, read 8 November 2026: support.servicem8.com/hc/en-us/articles/203336040-Jobs-Completed-Report
- 5. ServiceM8 Help Center, “What is the Advanced Reporting Pack Add-on”, read 8 November 2026: support.servicem8.com/hc/en-us/articles/202296784-What-is-the-Advanced-Reporting-Pack-Add-on
- 6. Xero Australia, “Project Tracking Software for Small Business”, read 8 November 2026: www.xero.com/au/accounting-software/track-projects/
- 7. Works Better, “Workflow Audit” and “Pricing”: worksbetter.ai/workflow-audit (Workflow Audit A$1,500) and worksbetter.ai/pricing (Job Profit Report A$5,900)
Not sure which to fix first?
Get a free fit check by email and I will say whether it is worth automating. No call needed. The next step is a A$1,500 workflow audit of one workflow, with a clear decision and a fixed quote if a build is worth doing.
Get a free fit check by email