Insight Job profit and reporting 6 min read

WIP report for trades: what is unbilled and what is at risk

By Renzo Demartini, Chartered Accountant ·

Drafted with AI, reviewed and spot-checked by me.

Job 3103 is quoted at A$15,000. The site lead says it is 50% done. Nothing is billed, so A$7,500 is unbilled. Cost so far is A$3,375 over the plan. Job 3103 has A$7,500 unbilled and A$3,375 of margin at risk. A weekly check finds both.
  1. Job 3103 is quoted at A$15,000.
  2. The site lead says it is 50% done.
  3. Nothing is billed, so A$7,500 is unbilled.
  4. Job 3103 has A$7,500 unbilled and A$3,375 of margin at risk. A weekly check finds both.
The build behind this topicA$5,900

Job Profit Report

Which numbers to agree before anyone builds a report, and what a job really made.

  • Simpro
  • Xero
  • MYOB
  • Excel
See job profitability reports for Simpro and ServiceM8
Fixed price · AUDYou decide what a person approves

A job is half done, nothing is billed and the costs keep landing. Your accounts show it only when the invoice goes out. A WIP report shows it now, job by job.

The short answer: a WIP report lists each open job with its cost so far, what you have billed and what is earned but not billed. Simpro and AroFlo have one.23 ServiceM8’s help pages list none.4 Run it weekly and look at two numbers: unbilled work and cost above plan.

  1. 01 · QuoteThe job is open

    Job app Job 3103 Open

    • Bathroom (sample)A$15,000.00
  2. 02 · CostCosts land on the job
    • Materials and labour coded
    • Cost so far A$9,000
  3. 03 · BilledInvoices are added up

    Accounts Invoices None

    • Billed to dateA$0.00
  4. 04 · CheckYou read the report

    Job 3103: A$7,500 unbilledCost is A$3,375 over plan

At the end of the day Steps 1 to 3 are numbers from your software. Step 4 is your decision.

What a WIP report shows

Four columns a WIP report holds, what each means and where one vendor describes it
Column What it means A vendor’s description
Cost so far What the job has cost to date AroFlo: costs incurred between two dates
Billed so far What you have invoiced AroFlo: invoices raised between two dates
Left to bill The job total less what is billed Simpro: job total less total billed, excluding tax
Over or under billed Billed against the share done AroFlo’s Project Over/Under Billings report

MYOB says “Work in progress is work that you have done for your clients but haven’t billed yet”, and that your records show a sale only when you bill.1 Simpro’s figure for what is not yet billed is the whole job total less what is billed, so ask how much of it is earned.2

What Simpro and AroFlo say about their reports

Simpro says its Job WIP report “displays jobs that were not invoiced in full or archived up to and including the specified date”.2 It says “The date that a job is archived determines whether it appears in this report”.2

AroFlo says its Task Work In Progress (WIP) By Date report is “useful to see what costs were incurred and invoices raised between specified dates”.3 Its Project Over/Under Billings report “answers the question “Am I allowed to invoice more money?””.3

What your software gives you

Five job and accounting packages, the report to use in each and what it shows
Software Report to use What it shows
Simpro Job WIP report Jobs not invoiced in full, as at a date
AroFlo Task WIP by Date and Project Over/Under Billings Costs and invoices in a date range, and over or under billing
ServiceM8 Jobs Completed report Completed jobs with no invoice sent. No WIP report in its help pages
MYOB AccountRight A month-end journal Plus and Premier only. Unbilled time on activity slips
Xero Projects Project reports Cost by task, with what is invoiced and what is to bill

ServiceM8’s Jobs Completed report has a “Not Invoiced” total: “the total value of Completed jobs which have not had an invoice sent to the client”.4 That counts finished jobs, not open ones. Xero’s page promises “a cost breakdown by task – including what’s been invoiced and what still needs to be billed”.6

Read five open jobs

Job 3103 holds A$7,500 of the A$10,600 not yet billed

Unbilled work, A$, sample

Earned less billed, job by job. Job 3102 is billed A$2,400 ahead of the work, so it shows none.

Illustrative figures, not client data.

Five sample open jobs with what each has earned, billed, left unbilled, cost and where cost is over plan
Job Earned Billed Unbilled Cost so far Over plan
3101 Switchboard upgrade A$7,200 A$6,000 A$1,200 A$5,400 A$0
3102 Kitchen rewire A$5,600 A$8,000 A$2,400 ahead A$5,600 A$1,400
3103 Bathroom A$7,500 A$0 A$7,500 A$9,000 A$3,375
3104 Hot water A$2,000 A$1,000 A$1,000 A$1,600 A$100
3105 Shed power A$2,400 A$1,500 A$900 A$2,400 A$600
Total A$24,700 A$16,500 A$8,200 net A$24,000 A$5,475

Sample data, not a client’s, in A$ excluding GST. Earned is the quote times the share done, which the site lead estimates. Plan cost is earned less a 25% quote margin. Over plan is cost so far above plan cost. This is my method, not a standard.

Three jobs hold A$5,375 of the A$5,475 over plan. Job 3102 is billed A$2,400 ahead, which helps cash and hides a cost problem.

The weekly check

  1. Run it as at today. Simpro’s report is a snapshot up to the date you choose.2
  2. Sort by unbilled. Bill what the work already supports.
  3. List jobs over plan. Cost so far above the plan cost.
  4. Ask for the share done. The site lead updates it on those jobs.
  5. Write the totals down. Next week’s check compares with them.

The unbilled figure rests on the share done, so use it as a prompt to check. Ask your accountant how work in progress is treated in your books.

Where a person stays in charge

The report

It adds up cost, billed and earned for each open job. It decides nothing.

The site lead

Gives the share done on each job. Every unbilled figure rests on this number.

You

You decide what to bill now and which jobs to review.

For one job costed from start to finish, see job costing for trades. For extra work never invoiced, try the free calculators.

The Job Profit Report puts each job’s costs and billed revenue side by side every week, A$5,900, in 3–4 weeks.7

If you are not sure which workflow to fix first, start with a Workflow Audit for A$1,500. It is a short brief by email and a read-only review of one workflow, up to two connected systems and a four-week sample of its records. The written report gives a clear decision (build it, change a setting or not yet) and a fixed quote if a build is worth doing.7 Start with a free fit check by email at the foot of this page.

Questions

What is a WIP report?

A list of open jobs with what each has cost, what has been billed and what is earned but not billed. MYOB defines work in progress as work you have done for clients but not yet billed.1

Does ServiceM8 have a WIP report?

Its help pages list none. The Jobs Completed report shows a Not Invoiced total for completed jobs, and the Advanced Reporting Pack exports a job list.45

What is the difference between unbilled and over billed?

Unbilled is work done and not yet invoiced. Over billed is invoiced ahead of the work done. AroFlo’s Project Over/Under Billings report is designed to show whether a project is over or under billed.3

How often should I run a WIP report?

Weekly is a sensible rhythm for an owner. Simpro’s report is a snapshot, so each run shows the position at the date you choose.2

Sources

Not sure which to fix first?

Get a free fit check by email and I will say whether it is worth automating. No call needed. The next step is a A$1,500 workflow audit of one workflow, with a clear decision and a fixed quote if a build is worth doing.

Get a free fit check by email

If you would rather have it built

Each topic has a fixed-price build behind it. The audit tells you which one is worth doing for your business.

Need more than one workflow? For strategy, board work and larger custom builds, I work through renzodemartini.com.

More insights

I get the systems you already have talking to each other and working together, so you get your nights and weekends back and are home for dinner.

Renzo

Renzo Demartini, Chartered Accountant

Works with Xero, MYOB, QuickBooks, n8n and Zapier, your job software, and whatever else you run.

Get a free fit check by email

Send the form with the workflow to fix and your email. Your software, team size and timing are optional, but they help. I reply by email, usually with a question or two, and tell you whether it's a fit. No call needed. If it is, the next step is the A$1,500 Workflow Audit.

Tell me what’s stuckStep 1 · Fit check · free, by email

Optional, but it helps me reply

Sending saves your details in HubSpot so I can reply. No mailing list. No payment is taken. How your enquiry is handled.